Katoomba RSL Rebuild
Date: Works were performed over 6 months commencing the 25th February 2019 and were completed on the
9th August 2019.
Scope: DJ DuRieu Air Conditioning has now completed the installation of all Mechanical Ventilation &
Air Conditioning onsite during the construction and completion of works for the rebuilding of
Katoomab RSL.
Systems included for this installation were Actron Air Packaged Units and Panasonic VRF Systems.
Additionally, DJ DuRieu installed all Kitchen and Toilet Exhaust Ventilation with all control wiring required for the
Packaged and VRF Systems to the Main Switch Board onsite.